Route 186 Paving Operations

Paving operations are scheduled for Route 186 beginning on Monday, June 5, 2023 through Thursday, June 8, 2023.

On June 5, 2023 work will begin north of the All American Canal bridge.

June 6 - North bound starting in the evening

June 7 - North bound and South bound work will be south of the All American Canal bridge.

June 8 - South bound starting in the evening.

Preparatory work starts at 2:00 am.  Chip seal starts at 7:00 am.  Asphalt concrete paving starts at 9:00 am expected to be completed before 6:00 pm.

 